The Difference between QC Inspections and Commissioning Inspections
Understanding Construction Quality Control
Construction
quality control is a type of management system that aims to ensure that the
deliverable fulfils the guidelines and standards laid by the client. These may
include completion of the project within the scope of predefined work as well
as avoiding disputes throughout the project’s life cycle. Quality is
established by the client and regulatory agencies, and is usually based on
regulatory and environmental guidelines. All the quality assurance procedures
and requirements are recorded in the construction quality management plan.
There are two
major facets of quality in construction: quality assurance (QA) and quality
control (QC). While quality assurance describes the quality management-specific
expectations and how to attain quality, quality control explains the plan to
achieve the same. The construction quality control manager oversees this plan
throughout different phases of the project.
Understanding Construction Commissioning
Building
commissioning is a methodical process of balances and checks to ensure that
building equipment and systems are constructed, designed, and operated for optimal
performance. The commissioningmanagement company brings an all-encompassing approach to the process of
design, and is accountable for thoroughly reviewing construction-specific
documentation, testing and validating the specific equipment post-installation,
and checking if building staff are trained properly to operate and maintain the
installed equipment.
Apart from
ensuring that building components, including cooling, heating, refrigeration
and water systems, and air handling work as they are expected to be, commissioning companies in the UK also aim to
lower maintenance and operational costs as well as improve the building’s energy
usage.
Although
installation contractors and design professionals are eventually accountable for
testing building systems and ensuring the quality of the installation, the commissioning
team provides a second pair of ears and eyes throughout the entire construction
process – checking for any deficiencies as well as preventing and resolving possible
issues before the building becomes fully operational.
QC Inspections vs. Commissioning Inspections
Commissioning
is a complex process, particularly the phase of transition to commissioning from
construction. However, with the proper documentation, it can be simplified
substantially. This is where the documents for QC and Commissioning Inspections
comes in.
There are basically
3 types of documents that have to be defined during the transition.
· Inspection Test Plans (ITPs)
· Mechanical Completion Checklists
· Pre-commissioning Checklists.
Let’s look at
these three types of documents in detail.
Inspection and Test Plans
Primarily,
these are part of the construction-specific quality control documents. Inspection
and test plans, acronymed as ITPs, list the quality inspections to be done in
order to confirm appropriate installation, once the systems are installed.
For instance,
a mechanical ITP is a checklist that includes the torque values that need to be
confirmed after equipment installation. Every bolt is torque-checked to see if they
are torqued appropriately. Another ITP example can be a checklist to verify and
confirm if equipment is installed correctly, including flushing of pipes to confirm
they contain no debris, pressure or leak testing to verify that the piping has no
leaks – and as part of the QC inspection documentation, it confirms that piping
has been installed correctly.
An example of
electrical ITPs can be a checklist, comprising all the inspections that need be
done on all cables after being pulled. This may include point-to-point testing
and Megger checking. Megger testing confirms that there is no damage to the
cables, with its dielectric properties being maintained well post installation.
Point-to-point testing confirms that the cable has been terminated appropriately
to the right terminal blocks in the automation cubicle. All ITPs are specific
to individual subsystems. Once all ITPs are done, the mechanical completion
documentation begins.
Mechanical Completion
Mechanical
completion is the process of formal handover to the commissioning team from the
construction team. Every mechanical completion contains all the ITPs associated
with a specific subsystem, and the mechanical completion checklist will include
the documentation, which is needed as part of that specific handover. Once all the
items listed in the mechanical completion checklist is completed, the checklist
is verified and signed off, indicating handover to the commissioning team, which
can then start with the pre-commissioning testing.
Commissioning Inspections
Commissioning
inspections are specified in pre-commissioning checklists. An example of a
pre-commissioning mechanical checklist can be a pump and a motor that need startup
for the very first time. In such a checklist, a bump test will be performed to verify
rotation, an uncoupled run will be done to see there are no issues, a coupled
run will be done to verify current draw, and an initial run-in will be done to check
flow and pressure rates.
An example of
a pre-commissioning electrical checklist can be powering up an automation
cubicle for the very first time. Such a checklist will include primary communication
checks, set-point and alarm checks, monitoring and control checks, loop checks,
and so forth. Once all pre-commissioning inspections are done, the systems can further
be tested during the commissioning testing phase.
To make their
entire commissioning inspection process faster, smoother and more efficient, most
commissioning management
companies rely on advanced commissioning management software like Cobia that helps ensure clear
tracking, traceability and accountability for every stage of the commissioning
process.
Conclusion
With the discussion above, the major difference between QC inspections and commissioning inspections is quite clear. Hence, it can be concluded that while QC inspections confirm that the equipment has been installed appropriately, commissioning inspections verifies that the equipment is functioning correctly.
Comments
Post a Comment