Best Practices of Commissioning to Follow During the Turnover Phase
Commissioning
- Turnover Phase
•
The
turnover phase of any construction project is a well-ordered shift of building
operations to the operation and maintenance (O&M) team from the project
commissioning management services team.
•
This
transition is physical, signifies completion of commissioning-specific
activities and involves knowledge transfer in the form of documentation.
•
A
successful transition is said to occur when the commissioning-specific
documentation is complete, fully organised, building systems are operable as per
the design and O&M personnel are trained appropriately to operate the
systems.
Up to
Date As-Built Documentation
•
Construction
projects are largely directed by design documents that elucidate and describe
countless working elements that require to be put together for a successful
turnover.
•
The
global commissioning management authority requires to be updated about the
modifications as they impact commissioned equipment and gets updated
documentation from the project team.
•
The
commissioning authority is not accountable for updating design-specific
documents, but they are responsible to ensure that red-lined updates are
reflected well in as-built drawings given to the owner – particularly,
mechanical as well as controls as-builts.
•
As-builts
provide the O&M personnel with comprehensive information, using which they
fix system problems, locate equipment, trend the performance of equipment and
transfer knowledge to new personnel as and when needed.
Well-Structured
Commissioning Documentation
•
Similar
to design documents, commissioning documentation should showcase the real
conditions of the commissioned systems.
•
At
the least, the commissioning final report should consist of the Commissioning
Plan and Performance Verification Criteria, Pre-Functional (PFC) and FPT notes,
the Commissioning Issues Log and a letter of acceptance, along with supporting
documents like Testing Adjusting and Balancing report, site visit reports, etc.
•
The
FPT and PFC notes are crucial resources that could aid present and future
building operators in developing a systems manual (if not provided in the
turnover phase) and help them with re-commissioning, three to five 5 years post
turnover.
Providing
a Systems Manual
• As part of the turnover package, the systems manual is not needed, unless the project seeks LEED Enhanced. Having said that, it’s another important resource that may ensure a successful turnover.
• Moreover, a systems manual should ideally include riser diagrams, control sequence highlights and control drawings. It is basically a tool that can be utilised by O&M personnel for troubleshooting, operating, and maintaining and monitoring building performance.
• In general, the re-commissioning plan should detail the following:
Ø Overview of the on-going commissioning process
Ø Responsibilities and roles of the commissioning team
Ø Schedule of re-commissioning
Ø List of the systems involved
Ø In-depth instructions for the replication of FPTs, implemented by the commissioning authority in the Acceptance phase.
Ø Re-commissioning documents to monitor outcomes
Ø Instructions and recommendations to set and track facility performance benchmarks
Comments
Post a Comment